DataVita has revised the power arrangements for its proposed 500MW AI data centre development near Glasgow, the Guardian reports. Its earlier plan promised more than 1GW of renewable capacity, including wind, solar and battery storage, connected directly to the data centres.
DataVita says its renewable energy commitment remains unchanged and that grid electricity will come through a renewable power purchase agreement. A proposed wind and solar park could provide direct connections later. The company remains backed by £202m in public guarantees from Britain’s national wealth fund.
UK data centre developments face a years-long wait for grid connections, while British energy costs are higher than in most of Europe. For companies planning AI infrastructure, the change underlines why a renewable supply agreement and a direct power connection should not be treated as the same commitment.